What is LCOE?

LCOE stands for Levelized Cost of Electricity, which is a measure of the average current cost of generating electricity from an asset over its lifetime. In practice, LCOE is typically used to help business owners and/or policymakers make decisions. LCOE is also often used to estimate the average price that a power generation asset must charge to reach its break-even point over its lifetime.

LCOE is a way to compare power plants that have diverse cost components. For example, a Coal-Fired Power Plant (PLTU) that uses coal as fuel will have fuel cost components throughout its operation, in addition to the initial cost of building the power plant. This is completely different from a Wind Power Plant (PLTB), which only has construction cost components, but has no fuel costs, and whose power plant operating costs are even close to zero. Because the LCOE calculation is based only on the cost of electricity incurred by a specific type of power plant without other parameters, different types of power plants with various generation technologies and financing schemes can be compared.


How to Calculate LCOE?

The LCOE formula and calculation model have been widely applied. The LCOE principle for a power plant is calculated from the sum of costs over the asset’s lifetime divided by the total amount of electricity generated over its lifetime. From the formula, it can be seen that anything that increases electricity production and/or reduces costs will lower the LCOE. Conversely, anything that reduces electricity production and/or increases costs will increase the LCOE.


What Factors Influence LCOE?

 

Initial Investment Cost / Capital Cost

 

The initial investment cost is divided into EPC (engineering, procurement, construction) and pre-development/construction costs of the power plant. EPC costs include the cost of purchasing equipment, installation costs, and costs for connecting to the electricity grid. Meanwhile, pre-development costs cover expenses for administration, consultation, project management, site preparation, environmental permitting, and other authorities such as surrounding residents. Another term often used for investment costs is CAPEX (capital expenditure).

In Indonesia, the initial investment cost component for renewable energy power plants tends to be greater than for fossil energy power plants. Factors contributing to this include high equipment costs due to technology that has not yet been developed massively and locally, as well as barriers to utilizing/importing cheaper foreign technology, and bureaucracy costs among stakeholders in the pre-development stage.

The initial investment cost directly affects the LCOE value. A larger initial investment cost will result in a higher LCOE.

 

Operational and Maintenance Costs

 

These are costs required periodically for the operation and maintenance of the equipment. The amount of the cost depends on the equipment technology, system size, and the size of the power plant location and the scope of maintenance needed. Another term for operational and maintenance costs is OPEX (operational expenditure).

If the initial investment cost component for renewable energy power plants is greater than for fossil energy power plants, the operational cost component is the opposite. The operational and maintenance costs for renewable energy power plants are smaller than for fossil energy power plants. For PLTU, for example, operational costs are burdened by fuel costs, in this case, coal, because its price fluctuates depending on the global market, and also by maintenance costs due to the many moving components in a coal-fired PLTU.

Just like the initial investment cost, operational and maintenance costs directly affect the LCOE value. Larger operational and maintenance costs will also increase the LCOE value.

 

Capacity Factor

 

The capacity factor is the ratio of the amount of electricity generated by a technology divided by the maximum amount of electricity that could be generated by a plant based on its installed capacity value (calculated assuming the plant always generates electricity according to its installed capacity value at all times). The value of this capacity factor is influenced by the availability of the energy source.

For fossil energy plants, the capacity factor depends on the availability of fuel and the readiness of the plant to operate. Whereas for renewable energy plants, the capacity factor will depend on the availability of the energy source in nature, such as the duration and intensity of sunlight for PLTS or the wind speed that turns the blades in PLTB.

The capacity factor value directly affects the LCOE calculation as a dividing factor. The higher the capacity factor of an energy source, the greater the electricity generated. If the electricity generated is greater, the LCOE value will be lower.

 

Financing Costs (Interest and WACC)

 

WACC stands for Weighted Average Cost of Capital, which is the average rate of return a company expects to pay to all its stakeholders, covering debt holders and equity shareholders (Vaidya). Because the funds needed to build a power plant are very large, the capital to build a power plant usually comes from shareholders (equity) and loans from financial institutions (debt). Of course, the capital providers do not simply provide capital but with the condition that there must be a “return” or profit from what they have given.

Debt interest and WACC will affect the cost of capital. The higher the debt interest and WACC, the greater the cost that needs to be returned to investors and to loan providers/financial institutions, and the LCOE value will be higher. For example, renewable energy power plants that require large initial capital are very vulnerable to changes in the WACC value.