Most renewable energy comes from nature, such as wind, sun, and water. However, natural conditions cannot always be relied upon. For instance, sometimes the wind blows strongly, and sometimes it doesn’t. Sunlight is also not always bright, such as at night or during the rainy season. To overcome the uncertain supply of these renewable energy sources, there is a technology called Pumped Hydro Energy Storage, commonly abbreviated as PHES, which can store electrical energy for when it is needed.
Operating Principle
PHES is essentially a Hydroelectric Power Plant (PLTA). However, PHES has an advantage over a regular PLTA. In a regular PLTA, water from a dam at a higher elevation flows according to the law of gravity to an outflow river at a lower elevation, passing through and driving a turbine. Meanwhile, in PHES, the water does not flow to an outflow river, but to a reservoir at a lower elevation. Thus, a PHES has two reservoirs: one at a higher elevation and one at a lower elevation.
The water that has flowed into the lower-elevation reservoir can be pumped back up to the higher-elevation reservoir. The purpose is to drive the turbine again when the demand for electricity is greater than the supply. Besides always being reliable when needed, PHES can also store the electrical energy it generates. Because of this, PHES is called a natural battery.
Potential and Installed Capacity in Indonesia
Based on research by IESR, the potential electricity that can be generated by PHES in Indonesia is 7,308.8 GWh. The province with the largest PHES potential is Central Sulawesi, followed by Aceh, Papua, East Kalimantan, and East Nusa Tenggara.
Currently, no PHES has been installed in Indonesia. The plan is for the first pumped storage PLTA development in Indonesia to be located in the upstream area of the Cisokan River, West Java, with a capacity of 1,040 MW.
Cost
The world’s largest pumped storage PLTA project in Hebei Province, PRC, required funds of $1.87 billion USD. The capacity of the world’s largest pumped storage PLTA is 3,600 MW. From this example, the estimated cost required to build a PLTA with a capacity of 1,040 MW is about $500 million USD. It should be noted that there will be factors that adjust the cost, such as differences in local terrain conditions, labor wages, and the technology used in the power plant. Meanwhile, the World Bank Executive Board has approved a loan of $380 million USD for the development of the first pumped storage PLTA in Indonesia.
Environmental Impact
PHES requires two dams on two plots of land at different elevations. During the construction of the dams, the ecosystem of the land and rivers in both places will be disturbed. However, the dams built do not require a large amount of land because the water reservoirs are generally designed to provide generation capacity for only a matter of hours or days. Furthermore, after the construction phase of the dams is complete, environmental benefits will emerge. The dams can be used for fish farming, as a water source for nearby residents, and as a regulator of river water discharge, thereby reducing the risk of flooding for surrounding settlements.